Replace Substation B5 for the Public Works Center
Great Lakes, Illinois

Contract Number: N68950-98-C-0116
Project Location:

Naval Training Center
Great Lakes , Illinois

Project Owner: Department of the Navy
Point of Contact: Sandy Ginalski, Project Manager

Address:

Engineering Field Activity, Midwest
201 Decatur Ave. , Building 1A
Great Lakes , Illinois 60088

Phone/Fax Number: (847) 688-4950 ext. 407
(847) 6888-2648
Initial Contract Dollar Value: $1,470,674
Final Contract Dollar Value: $1,693,071
Period of Performance: December 2, 1998 to July 19, 2000

Description

This project consisted of the provision of the following:

  • Providing one line-up of 35kV Vacuum Switchgear
  • Providing one 7.5MVA power transformer
  • Providing one line-up of 15kV Vacuum walk-in protected aisle switchgear
  • Installation of 4 manholes
  • Installation of 3 - 600Amp 35kV Sectionalizing Pedestals
  • Installation of 600' - 6" Duct Bank,
  • Installation of 11,500' 35kV Okonite 500 MCM Power Cable

Comments

Scheduling delays on this project were due to differing site conditions and additional work on a footbridge/trestle not anticipated in the original contract. As late as March 30, 2000 excavation around the existing trestle piers exposed vertical wooden supports that had rotted below grade. As a result, new concrete "pile caps" are being added at nine locations. Electrical changes to the contract have been minor. Trestle changes have caused delays and price increases.

Performance Evaluation

Overall Performance Evaluation: Outstanding

Quote from performance evaluation dated October 30, 2000:

“The contractor, Webb Electrical, with Bruce Kelly as the Superintendent/CQC did an outstanding job of providing the government with an excellent new substation for up-grading the high voltage system onboard the base. The effort exerted to overcome numerous unforeseen conditions and maintain their construction schedule was completed in a professional comprehensive manner.”